Belgian region orders Google to halt data centre construction

Greenpeace publishes report showing tech firm is continuing to build despite planning appeal still unresolved

Belgian region orders Google to halt data centre construction

Walloon regional authorities ordered Google to halt construction at its data centre site near Farciennes/Aiseau-Presles after inspectors found the building almost finished despite refused changes to its planning permission, the Guardian reported. About 300 workers were given a stop-work order that was confirmed in writing to Google; Google said it remained committed to dialogue, and its appeal is due to be heard on Jan. 7.

What it means

Google has been ordered to stop construction at its Belgian data centre site, affecting workers there. Google's appeal is due to be heard on Jan. 7, which will determine whether work can resume.

Read the original on the Guardian